Party Wall Guide for Extensions & Conversions
If your extension or loft conversion involves a shared wall, building on the boundary or digging near a neighbour's foundations, the Party Wall etc. Act 1996 probably applies. Here's what to do and when.

When the Act applies
You must give notice for three main types of work.
- Work to an existing party wall — e.g. cutting in beams for a loft conversion or removing chimney breasts
- Building a new wall on or astride the boundary line
- Excavating within 3 m of a neighbour's structure (6 m for deep foundations), e.g. extension foundations
Serving notice and timescales
- Party structure notice: at least 2 months before work starts
- Line of junction notice (new boundary wall): at least 1 month
- Notice of adjacent excavation: at least 1 month
- Notices last one year — start within that time
- Your neighbour has 14 days to respond
If your neighbour consents or dissents
If they consent in writing, you can proceed (a schedule of condition is still wise). If they dissent or don't reply within 14 days, a dispute arises and surveyors are appointed to agree a Party Wall Award.
- Agreed surveyor: one surveyor acts for both owners
- Two surveyors: one each, who select a third if they disagree
- The building owner normally pays the surveyors' fees
Typical costs
Allow roughly £700–£1,500 per neighbour where a single agreed surveyor acts, and more where each owner appoints their own surveyor.
Practical tips
- Talk to your neighbours before sending formal notices
- Take dated photos of their side of the wall
- Include party wall timescales in your programme
- Your designer and structural engineer can prepare the information needed
Frequently asked questions
This page provides general, preliminary information. It is not a planning decision, formal valuation or professional appointment. Appropriate checks and current planning information may be required. Last reviewed 2026-06-01.